Ely bypass overspend: the auditors report

The County Council’s auditors, LGSS, have carried out a full and extensive audit of the overspends on the Ely bypass. The resulting report has been presented to the council’s Audit and Accounts Committee.

The report found that “due to the desire of key stakeholders to get the project completed in the shortest timescales possible, and the consequent design of the Contract, insufficient time was given to the project planning stage which, when combined with the type of Contract used during construction, meant that the true costs of the project were not available to officers nor Members until the project was near completion”.

The report made six recommendations:

  1. Consideration should be given to whether the Constitution should be adapted to incorporate limits to delegating authority away from Committees, particularly when there are significant financial implications. In instances where officers are given delegated authority to make significant decisions outside of their ordinary powers as stated in the Scheme of Delegation, even in consultation with some Members, then reports should be provided to relevant Members or Committee which outline the decision that was taken, particularly in high-risk areas or projects.
  2. Future projects should follow a procurement and design stage which takes full account of advice from key officers, the procurement team, any external consultants and suppliers. This should include a provision for extending certain phases of projects; such as the design stage. The relevant Committee on any project should be made aware of any risks associated with the procurement/design process being recommended to them, including any impact this might have on the final costs of the Project.
  3. In instances such as the Ely Bypass project, with numerous spend increases compared the original budgeted and contracted amounts, regular updates should be taken to the relevant Committee. These updates should include the current price and the most up-to-date target/expected final price, along with a detailed project risk register, which should give an overview of the key areas where further price increases may occur, as well as the likelihood of these price increases.
  4. The Project Board should insist on the most up-to-date figures on cost at all times, even if the final expected figure is not known. Further, rather than being left to individual officers to decide when the Committee is informed on the progress being made on the project or on any price increases, this decision should have been made by the Project Board, who should dictate when any risks on the project, including any overspends, are presented to Committee.
  5. Directors should manage, or if necessary escalate, situations where there is pressure to pursue actions that do not follow normal governance rules. It is recommended that a simple procedure is put in place for instances requiring escalation through a short report to the next available Joint Management Team. Regarding this recommendation, the Internal Audit team will always be available to support officers with emailed advice on procedures should there be a need.
  6. Rather than waiting for the Project Board meetings for Members of the Board to be told about the Contract, the Project Board should be provided with the Dashboards every month, in order to allow any concerns which the dashboards may raise to be discussed as early as possible Future projects should follow a procurement and design stage which is in line with advice from key officers, the procurement team and any external consultants.

Image © Copyright John Sutton and licensed for reuse under this Creative Commons Licence.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.